Afren

  • Case-Study-CS601

About the Project

In December 2009, Mercator Lines Ltd. were awarded the contract for the EBOK MOPU conversion. The contract included the provision of project management, engineering, procurement and installation & commissioning supervision for the 100,000 bbl/d topsides process package. The project was completed within 11 months from the contract award.

Case-Study-CS602

The scope of supply for the project included:

  • Process facilities capable of up to 100,000 bbl/d fluids with up to 75% water cut production
  • 40,000 bbl/d sea water lift, treatment and injection @ 1,800 psi
  • Gas lift compression of up to 10 MMscf/d @ 1,400 psi and 7MW of power generation (dual fuel turbines)
  • Stabilised crude and fuel gas was exported to an FSO

Case-Study-CS603

These case studies provide examples of the projects members of the Influit team have undertaken whilst working for previous companies.